Net Metering in India: How to Sell Excess Solar Power to the Grid
Complete guide to net metering in India covering how it works, state-wise policies, application process, financial returns, and strategies to maximize your solar electricity savings.
What is Net Metering and How Does It Work in India?
Net metering is a billing arrangement that allows solar panel owners to export excess electricity to the grid and receive credits on their electricity bill. It's the mechanism that makes rooftop solar financially viable for Indian households. This comprehensive guide explains how net metering works, state-wise policies, and how to maximize your savings.
How Net Metering Works
The Basic Concept
- Your solar panels generate electricity during daytime
- Your home consumes some of this solar electricity directly
- Any excess solar electricity flows into the grid through a bidirectional meter
- When you need more power than solar produces (night/cloudy days), you draw from the grid
- At the end of the billing cycle, you pay only for the net difference
Example Calculation
| Month | Grid Import (kWh) | Solar Export (kWh) | Net Consumption | Bill Amount |
|---|---|---|---|---|
| January | 250 | 180 | 70 kWh | ₹560 |
| April | 300 | 350 | -50 kWh (credit) | ₹0 (50 kWh carried forward) |
| July | 280 | 200 | 80 kWh (minus 50 credit = 30) | ₹240 |
Without solar: ₹2,000-5,000/month. With net metering: ₹200-800/month. That's 70-90% savings!
Types of Metering
Net Metering
Your meter runs backward when you export. You pay only for the net difference between import and export. This is the most beneficial for consumers and is available in most Indian states.
Gross Metering
All solar generation is exported to the grid, and all your consumption is imported from the grid. You get paid a fixed rate (Feed-in Tariff) for your exports. Typically less beneficial than net metering for residential consumers.
Net Billing
Similar to net metering, but excess solar is credited at a different (usually lower) rate than your consumption tariff. Some states are transitioning from net metering to net billing for larger installations.
State-Wise Net Metering Policies (2026)
| State | Metering Type | Capacity Limit | Excess Credit | Validity |
|---|---|---|---|---|
| Delhi | Net Metering | Up to sanctioned load | Carried forward annually, settled at average pooled cost | 25 years |
| Maharashtra | Net Metering | Up to 1 MW | Carried forward within financial year | 25 years |
| Gujarat | Net Metering | Up to 50% of sanctioned load | Carried forward, settled at year-end at ₹2.25/kWh | 25 years |
| Karnataka | Net Metering | Up to 1 MW | Bought by DISCOM at ₹2.90/kWh | 25 years |
| Tamil Nadu | Net Metering + Net Feed-in | Up to 100% of sanctioned load | Settled at average pooled cost | 25 years |
| Rajasthan | Net Metering | Up to 1 MW | Carried forward, settled at ₹2.88/kWh | 25 years |
| UP | Net Metering | Up to 500 kW | Carried forward within financial year | 25 years |
| MP | Net Metering | Up to 500 kW | Carried forward | 25 years |
How to Apply for Net Metering
Step-by-Step Process
- Install Solar System: Choose an empanelled vendor and install your rooftop solar system
- Apply to DISCOM: Submit application through your state DISCOM portal with:
- Property ownership proof
- Electricity bill copy
- Solar system details (capacity, vendor, components)
- Single line diagram (provided by installer)
- Structural stability certificate (for large systems)
- Feasibility Check: DISCOM verifies grid capacity at your distribution transformer
- Meter Installation: DISCOM installs a bidirectional meter (typically free or ₹1,000-2,000)
- Inspection: DISCOM inspects the installation for safety compliance
- Agreement: Sign a net metering agreement (typically 25-year validity)
- Commissioning: System goes live with net metering
Timeline
The complete process takes 30-90 days depending on your DISCOM. Some states have streamlined this to 15-30 days.
How to Maximize Net Metering Benefits
1. Right-Size Your System
Install a system that generates roughly 80-100% of your annual consumption. Oversizing means excess credits that may be settled at lower rates.
2. Shift Heavy Usage to Daytime
Run washing machines, water heaters, and ACs during solar peak hours (10 AM - 3 PM) to directly consume solar power instead of exporting at lower credit rates.
3. Monitor Your Generation
Most modern inverters have WiFi monitoring. Track your generation vs consumption to optimize usage patterns.
4. Seasonal Adjustment
Solar generation peaks in March-May and dips in July-August (monsoon). Plan your electricity usage accordingly.
5. Battery Backup Consideration
With net billing replacing net metering in some states, storing solar in batteries and using it yourself may become more economical than exporting. Hybrid systems with batteries are increasingly popular.
Common Net Metering Issues
- DISCOM delays: Some DISCOMs take months to install net meters. Escalate through consumer forums or the state electricity regulatory commission.
- Transformer capacity: If your local transformer is already at capacity, DISCOM may reject your application. Solutions include upgrading the transformer (cost shared) or waiting for capacity expansion.
- Meter accuracy: Request periodic meter testing if you suspect inaccurate readings. DISCOMs are required to test on request.
- Credit settlement: Track your credits carefully. Some DISCOMs have been known to not carry forward credits properly.
Financial Returns with Net Metering
| System Size | Annual Generation | Annual Savings | Payback Period |
|---|---|---|---|
| 1 kW | 1,400-1,600 kWh | ₹10,000-14,000 | 4-5 years |
| 2 kW | 2,800-3,200 kWh | ₹20,000-28,000 | 3.5-4.5 years |
| 3 kW | 4,200-4,800 kWh | ₹30,000-42,000 | 2.5-4 years |
| 5 kW | 7,000-8,000 kWh | ₹50,000-70,000 | 3-5 years |
The Future of Net Metering in India
Net metering policies are evolving. Some states are moving toward net billing or gross metering for new installations above 10 kW. For residential consumers (below 10 kW), net metering is expected to remain available through 2030. The addition of time-of-day tariffs may further incentivize solar with battery storage, as evening/night consumption rates increase.